Building Timeline

18.12.12 - Site Scrape
07.01.13 - Retaining wall commenced
10.01.13 - Retaining wall completed
15.01.13 - Certification for retaining wall rejected
17.01.13 - Peiring completed
22.01.13 - Pipe work prepared and completed
22.01.13 - Porta Loo delivered
25.01.13 - Onsite meeting with supervior to check progress
25.01.13 - Retaining wall being completed... but not approved
01.02.13 - Frame work started for slab
04.02.13 - Frame work redone due to weather. Waffle Pods installed
06.02.13 - Slab poured
11.02.13 - Temporary fencing delivered & electrical box installed
11.02.13 - Dirt spread around slab
12.02.13 - Temporary fencing up & retaining wall completed.....
13.02.13 - Metal frames delivered
06.03.13 - Frame fully errect
06.03.13 - Windows delivered
07.03.13 - Windows installed
07.03.13 - House wrap begun